Information on retained water
The total retained volume of water is hard to assess as the Fornebu plan consists of multiple NWRM and Green Infrastrucutre measures
Increased water storage
230
Increased water storage unit
m3/ha
Information on runoff reduction
Large qualitiative reductions in runoff peaks could be expected
Information on Peak flow rate reduction
Large qualitative reductions in peak flow could be expected when compared to the old Fornebu airport
Ecosystem erosion control
0
Water quality overall improvements
Positive impact-WQ improvement
Information on Water quality overall improvements
based on mdeolling results and design criteria
Water quality Improvements Phosphorus (P)
60
Water quality Improvements (P) unit
% reduction pf pollutant
Water quality Improvements Nitrogen (N)
40
Wq Improvements n unit
% reduction pf pollutant
Water quality Improvements Total Suspended Solid (TSS)
80
Water quality Improvements (TSS) unit
% reduction pf pollutant
Water quality Improvements Copper (Cu)
65
Water quality Improvements (Cu) unit
% reduction pf pollutant
Water quality Improvements Zinc (Zn)
45
Water quality Improvements (Zn) unit
% reduction pf pollutant
Soil quality overall soil improvements
Positive impact-SQ improvement
Information on Soil quality overall soil improvements
improvements related mainly to brownfield cleanup and removal of 200000m3 contaminated soil
Information on Soil quality overall soil pollution
brownfield improvement included removal of contaminated soil, PAH, oil and deicing fluids were all problems