- Improvement of water retention capacity in the system
- Reduction of flood vulnerability due to a better developed riparian forest
- Improvement of water quality
* The economic activity of the region is based on traditional activities, which occupied the riversides of the Odelouca with fruit trees (citrus) annual irrigation crops, vegetables gardens and livestock. Traditionally, landowners use as protection for flood risk ripraps and earth embankment, proving memory on past flood events (causing relevant damages). Despite the initial mistrust in the measures to be implemented, most landowners gave their permission to develop works within their property, which will have direct benefits on flood protection, improved soil composition, water availability, and landscape improvement.
Ancillary benefits information
- Water retention in riverbanks and improvements in infiltration capacity will provide better water security (reliability of supply and resilience to drought). Water provision to deliver water services to the economy, in particular to irrigated agriculture
- Flood security and protection (delay on flood peaks)
- Amenities (associated to habitat protection): fish and plants, tourism, recreation, and others
- Sediment retention
- Carbon fixation
- Wildlife habitats and ecological corridors
- Streambanks stabilization
- Providing shade, organic matter, food for streams and their biota
- Filtration of chemicals and other pollutants
Costs capital information
3,4 - 9,2 €/m2 (median: 4,5 €/m2): Cost range for geotextile application in similar projects carried out in Spain (Mediterranean basins)
20,7 €/m2: Cost of the application of geotextile (coco fibre) plus willow stakes in Spain.
Vegetated rock armour
72,3 €/m2: Live cribwalls (Krainer wall): 5 wood logs [h=2m; x=20cm] plus 30 willow (alive) stakes.
Vegetated gabions
3078 €/ha: Vegetation clearance (this is the average cost of 21 implemented projects in Spain). The range was 428 -7019 €/ha
25203 €/ha: Re-vegetation (this is the average cost of 21 implemented projects in Spain). The range was 1614 - 80249 €/ha
Costs maintenance information
The average annual maintenance cost for bioengineering measures (using alive material) is 5% of the investment cost. It is foreseen that maintenance should be 3 year long, thus the total maintenance cost could be estimated as the 15% of the investment cost
Costs total information
This includes the total cost of the initial sub programme of measure (avifauna, fish fauna, riparian galleries and monitoring studies) (5,430,664 €) and the budget of the Project RICOVER for rehabilitation of riparian galleries (267,636 €).
Ecosystem improved biodiversity
1
Information on Ecosystem improved biodiversity
The Odelouca River is part of the Natura 2000 Network, as it is the habitat of two endemic fish species and the Iberian Lynx. By recovering the river functions, and retaining water, a proper functioning of ecosystems to support the habitat of these species is possible.
Ecosystem provisioning services
0
Ecosystem impact climate regulation
No information available